2017 0525 50fifty Update

On In Construction Update

All major basement slab on grade is complete. Our second luffing crane is up and operational, just in time for the precast erection which started this week. The site will undergo significant changes over the next four months as the structure rises from below grade 2 levels, to six levels above. Six levels of steel (office) construction will occur on top of the precast (garage) and is scheduled to start in September.