2017 0328 50Fifty Update
On
In
Construction Update
Majority of perimeter drains are installed, and the Sand/Oil interceptor is installed
Core 1 (East Stair) cast-in-place starter walls have been poured and the formwork has been removed. The mat slab has been backfilled up to the top of mat slab.
Core 2 & 3 mat slab framing has been removed and vertical waterproofing is installed and lapped over the top of the mat slab. Drainage board has been installed on the vertical face of the mat slab.
Mat slab for Core 4 is installed, formwork is still in place on its vertical sides. Framing for the cast in place starter walls around the Elevator Shaft is in progress