2017 0328 50Fifty Construction Update

On In Construction Update

Majority of perimeter drains are installed, and the Sand/Oil interceptor is installed

Core 1 (East Stair) cast-in-place starter walls have been poured and the formwork has been removed. The mat slab has been backfilled up to the top of mat slab.

Core 2 & 3 mat slab framing has been removed and vertical waterproofing is installed and lapped over the top of the mat slab. Drainage board has been installed on the vertical face of the mat slab.

Mat slab for Core 4 is installed, formwork is still in place on its vertical sides. Framing for the cast in place starter walls around the Elevator Shaft is in progress

2017 0221 50Fifty Construction Update

On In Construction Update

Over half of the drilled piers are complete. Perimeter drains are also being installed. Void forms and grade beams are being constructed. Some standing water has accumulated, but no more than expected.

2017 0207 50Fifty Construction Update

On In Construction Update

Excavation of 50Fifty is just about complete, and we’ve started drilling piers for the foundation. Rebar cages are being fabricated at the south end of the site, and temporary power is in place at the bottom of the excavation pit.

2016 1121 50Fifty Groundbreaking

On In Construction Update

Several years of grinding to get to this point, thanks to all these people. Today we celebrate, tomorrow we get back to work. Building core and shell completion to occur in the 3rd quarter of 2018. Going to be a good one!

2016 1029 Demolition Complete

On In Ground Breaking

The demolition of the existing building is complete! Shoring, earthwork, and drilled piers to start in November. Look for an official ground break announcement in the next few weeks.

2016 1026 5050 Demolition

On In Construction Update

It’s an exciting time at the 5050 S Syracuse job site. Hensel Phelps has mobilized, and the existing building is coming down. We expect to have an official ground breaking ceremony some time next month.